CVRD issued  new tender proposal request for construction services  on May 17th, 2018  for completion of  sections of the Cowichan Valley Trail along the E&N rail corridor between Cook Street (Chemainus) through to Stocking Creek Park (Saltair),  (approximately 4.3 km). Trail construction will include a 27metre span pedestrian bridge, crossing Stocking Creek.

Closing date to submit construction service proposal: June 7th , 2018 at 2:00 pm CVRD.